CAPM (Certified Associate in Project Management) Practice Exam 2025 - Free CAPM Practice Questions and Study Guide

Question: 1 / 885

How is Schedule Variance (SV) calculated?

SV = PV - EV

SV = EV - PV

Schedule Variance (SV) is calculated by subtracting the Planned Value (PV) from the Earned Value (EV). This calculation helps in determining whether a project is ahead of or behind the planned schedule at a specific point in time. In this case, SV = EV - PV is the correct formula.

Option A (SV = PV - EV) is incorrect as it would result in a negative value, which does not accurately represent schedule variance.

Option C (SV = AC - PV) involves comparing the Actual Cost (AC) with the Planned Value (PV) and is related to Cost Variance, not Schedule Variance.

Option D (SV = PV + EV) is also incorrect because adding PV to EV does not provide an accurate representation of the variance between the planned and earned values in the schedule.

Get further explanation with Examzify DeepDiveBeta

SV = AC - PV

SV = PV + EV

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy