CAPM (Certified Associate in Project Management) Practice Exam 2025 - Free CAPM Practice Questions and Study Guide

Question: 1 / 885

Which one of these is NOT listed as a type of work performance data?

Actual costs

Number of meeting hours

Work performance data includes information such as actual costs, start and finish dates, and number of defects. These data points help the project team assess performance and progress. However, the number of meeting hours is not typically classified as work performance data in project management. While meetings are essential for communication and coordination, the number of meeting hours is considered more of a project management metric rather than work performance data.

Get further explanation with Examzify DeepDiveBeta

Start and finish dates

Number of defects

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy