CAPM (Certified Associate in Project Management) Practice Exam 2026 - Free CAPM Practice Questions and Study Guide

Session length

1 / 1265

What is the schedule baseline?

A tentative project schedule

A detailed risk analysis

The approved version of a schedule model for comparison to actual results

The schedule baseline is the approved version of a schedule model that serves as the basis for measuring and monitoring project progress. Option A, a tentative project schedule, may not have been approved and is subject to change. Option B, a detailed risk analysis, is a different aspect of project planning and does not pertain to the schedule. Option D, a preliminary project budget, is also a different aspect of project planning and does not specifically pertain to the schedule. Therefore, the best answer is C.

Get further explanation with Examzify DeepDiveBeta

A preliminary project budget

Next Question
Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy