Among the listed tools and techniques for Plan Risk Management, which involves discussing potential risks and their impacts?

  1. Meetings

  2. SWOT Analysis

  3. Expert Judgment

  4. Documentation Reviews

The correct answer is: Meetings

The correct answer is "Meetings". Meetings involve discussing potential risks and their impacts with stakeholders and project team members, making it a useful tool for Plan Risk Management. This allows for a collaborative approach in identifying potential risks and understanding their potential impacts on the project. Options B, C, and D are incorrect because they are not specifically focused on discussing potential risks and their impacts. SWOT analysis is used to identify strengths, weaknesses, opportunities, and threats, which may include risks but is not the primary purpose of this technique. Expert judgment and documentation reviews involve using external sources for information and decision making, rather than actively discussing potential risks.