CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the CAPM Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


How is ETC calculated when past variances are considered atypical?

  1. ETC = AC - EV

  2. ETC = BAC - AC

  3. ETC = BAC - EV

  4. ETC = EV - AC

The correct answer is: ETC = BAC - EV

When past variances are considered atypical, it implies that the project's actual performance is not reflective of what was initially planned. In such situations, it is more appropriate to rely on the original project baseline to estimate the remaining work. Therefore, the correct formula to calculate the Estimate to Complete (ETC) in this scenario is ETC = BAC - EV. Option A (ETC = AC - EV) and Option D (ETC = EV - AC) are incorrect because they are formulas based on current project performance, which would not be suitable when past variances are considered atypical. Option B (ETC = BAC - AC) is also not the correct choice as it does not account for the work that still needs to be completed based on the original project baseline.