CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the CAPM Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


How is the original estimate technique for finding EAC calculated?

  1. EAC = AC/(BAC - EV)

  2. EAC = AC + BAC

  3. EAC = BAC/EV

  4. EAC = BAC - AC

The correct answer is: EAC = AC/(BAC - EV)

The original estimate technique for finding EAC is calculated by dividing the actual cost (AC) by the difference between the budget at completion (BAC) and earned value (EV). Option A is the only one that utilizes the concepts of actual cost, budget at completion, and earned value in its calculation. Option B simply adds the actual cost to the budget at completion, which does not accurately reflect the remaining work to be completed. Option C divides the budget at completion by the earned value, which does not consider the actual cost already incurred. Option D subtracts the actual cost from the budget at completion, which does not take into account the earned value or remaining work.