The Inputs of Identify Risks include all of the following EXCEPT:

  1. HR Management Plan

  2. Quality Management Plan

  3. Change Management Plan

  4. Schedule Management Plan

The correct answer is: Change Management Plan

The Inputs of Identify Risks includes all project related documents and plans which might be impacted by the occurrence of risks. This includes the HR Management Plan, Quality Management Plan, and Schedule Management Plan. The Change Management Plan, however, is not included because it deals with managing changes to project scope, which is not directly related to identifying risks. Therefore, it is not considered an input for this particular process.