What are discretionary dependencies?

  1. Dependencies that are within the team's control

  2. Options for accomplishing activities with other orders and resources

  3. Dependencies that cannot be changed

  4. External factors not under the team's control

The correct answer is: Options for accomplishing activities with other orders and resources

Discretionary dependencies refer to optional choices for completing tasks with outside resources and orders. This means that the team has the ability to change or adjust these dependencies as needed, depending on their specific goals and circumstances. The other options are incorrect because they either refer to dependencies that cannot be adjusted or they imply that the team has complete control over these dependencies. In reality, discretionary dependencies allow for flexibility and decision-making within a team while completing their tasks.