What are internal dependencies?

  1. Dependencies outside the team's control

  2. Options for different activity sequences

  3. Relationships between defined project activities

  4. Dependencies that cannot be changed

The correct answer is: Relationships between defined project activities

Internal dependencies refer to relationships between defined project activities. This means that these dependencies exist between tasks that have to be completed by the same team or within the same project. These dependencies are within the team's control as they are part of the project plan and can be adjusted or managed by the project team. Options for different activity sequences (B) do not refer to dependencies, but rather alternate paths or ways of completing tasks. Dependencies outside the team's control (A) would refer to external factors or tasks that are not within the control of the project team. Dependencies that cannot be changed (D) would not be considered internal dependencies as they are not able to be adjusted by the team.