What are the deliverables of the termination and close phase?

  1. Formal Acceptance and Documented Results

  2. WBS and Schedule Baseline

  3. Execution Results for Work Packages

  4. Scope Statement

The correct answer is: Formal Acceptance and Documented Results

The deliverables of the termination and close phase refer to the final output of a project. Option A, formal acceptance and documented results, is the most accurate as it includes both the formal acceptance of the project and the documentation of the final results. Option B, WBS and schedule baseline, are deliverables of the planning phase and are not specific to termination and close. Option C, execution results of work packages, are also not specific to termination and close as they are a product of the execution phase. Option D, scope statement, is a deliverable of the initiating phase and is not specific to termination and close. Overall, option A is the most comprehensive and accurate answer.