What are the inputs for identifying stakeholders?

  1. Project charter, procurement docs, enterprise env factors, org process assets

  2. Stakeholder analysis, expert judgment, meetings

  3. Stakeholder register

  4. Assessment and classification only

The correct answer is: Project charter, procurement docs, enterprise env factors, org process assets

The correct answer is A. Project charter, procurement documents, enterprise environmental factors, and organizational process assets are the inputs for identifying stakeholders. Option B is incorrect because stakeholder analysis, expert judgment, and meetings are tools and techniques used in the Identify Stakeholders process, not inputs. Option C is incorrect because the stakeholder register is an output of the Identify Stakeholders process, not an input. Option D is incorrect because assessment and classification are part of the tools and techniques used in the Identify Stakeholders process, not inputs.