What are the inputs of plan schedule management?

  1. Project management plan, Project charter, Enterprise env factors, Org process assets

  2. Work performance data, Project schedule, Risk register, Stakeholder register

  3. Project scope statement, Resource calendars, Project team assignments, Quality metrics

  4. Resource availability, Stakeholder risk appetite, Team contracts, Activity resource requirements

The correct answer is: Project management plan, Project charter, Enterprise env factors, Org process assets

The inputs of plan schedule management include the project management plan, project charter, enterprise environmental factors, and organizational process assets. These inputs are critical for setting the direction and establishing the guidelines for creating and managing the project schedule effectively. Options B, C, and D, while related to project management processes, are not specifically the inputs for plan schedule management. Option B includes work performance data, project schedule, risk register, and stakeholder register which are more related to monitoring and controlling project work. Option C involves project scope statement, resource calendars, project team assignments, and quality metrics which are more aligned with other project management processes. Option D consists of resource availability, stakeholder risk appetite, team contracts, and activity resource requirements which are not directly related to planning the project schedule.