What are the inputs of plan stakeholder management?

  1. Project scope statement, WBS, Quality metrics, Risk register

  2. Project management plan, Stakeholder register, Enterprise environmental factors, Organizational process assets

  3. Marketing plan, Financial documents, Resource calendars, Supplier contracts

  4. Change requests, Project schedule, Cost forecasts, Quality control measurements

The correct answer is: Project management plan, Stakeholder register, Enterprise environmental factors, Organizational process assets

The inputs of plan stakeholder management are essential documents or components that are necessary to successfully manage stakeholders throughout the project. Option A is incorrect because the project scope statement, WBS, quality metrics, and risk register are part of the project management plan, which is already listed in option B. Option C is incorrect because the marketing plan, financial documents, resource calendars, and supplier contracts are not specific to stakeholder management and do not provide relevant information on stakeholder needs and expectations. Option D is incorrect because the listed items are components of other processes and do not specifically pertain to stakeholder management. Thus, option B is the most suitable answer as it includes the necessary documents, such as the stakeholder register and project management plan, and environmental factors and assets that are crucial for effective stakeholder management.