What are the outputs of plan communications management?

  1. Communications management plan and project documents updates

  2. Project management plan update

  3. Risk register update

  4. Stakeholder engagement plan

The correct answer is: Communications management plan and project documents updates

The outputs of plan communications management include the communications management plan and project documents updates. Choice B is incorrect because updating the project management plan is only one aspect of plan communications management, while choice C, updating the risk register, is not a direct output of this process. Choice D, the stakeholder engagement plan, is an output of the identify stakeholders process, not plan communications management. It is important to note that while these outputs may be related to other project management plans and documents, they are not the same as the communications management plan and project documents updates.