What are the outputs of plan risk responses?

  1. Risk mitigation plans

  2. Project management plan updates, project documents updates

  3. Quality control measurements

  4. Project funding requirements

The correct answer is: Project management plan updates, project documents updates

Outputs of plan risk responses include updates to the project management plan, including cost and schedule baseline, and project documents such as risk register, risk response plan, and risk reassessment. Options A, C, and D are incorrect as they do not specifically state the outputs of plan risk responses. Risk mitigation plans, quality control measurements, and project funding requirements may be necessary as part of the risk response plan, but they are not the only outputs of the process. Option B includes the most complete and accurate list of outputs for this process.