CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the CAPM Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What are the outputs of the create WBS process?

  1. Project management plan

  2. WBS, WBS dictionary, scope baseline, project document updates

  3. Accepted deliverables

  4. Scope management plan

The correct answer is: WBS, WBS dictionary, scope baseline, project document updates

The outputs of the create WBS process are the WBS, WBS dictionary, scope baseline, and project document updates. The WBS is a visual representation of the project scope broken down into manageable components, while the WBS dictionary provides a detailed description of each work package within the WBS. The scope baseline is the approved version of the project scope statement, WBS, and WBS dictionary. Project document updates can include any changes made to the project management plan, project scope statement, or any other project documents. Project management plan, accepted deliverables, and scope management plan are incorrect because they are either inputs or outputs of other project management processes, not specifically the create WBS process.