CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the CAPM Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What are the three types of project network schedule calculations?

  1. Forward pass, backward pass, float

  2. Project initiation, planning, execution

  3. Resource allocation, risk management, control

  4. Cost estimation, time management, quality control

The correct answer is: Forward pass, backward pass, float

The correct answer is A: Forward pass, backward pass, float. In project management, the three types of project network schedule calculations are forward pass, backward pass, and float. - Forward pass calculation determines the earliest start and finish times for each activity in a project schedule. - Backward pass calculation determines the latest start and finish times that activities can start and finish before delaying the project. - Float, also known as slack, is the amount of time an activity can be delayed without delaying the project completion date. Options B, C, and D are all incorrect as they do not represent the three types of project network schedule calculations.