What can be an enterprise env factor influencing perform qualitative risk analysis?

  1. List of identified risks

  2. Industry studies of similar projects by risk specialists

  3. Risk urgency assessment

  4. Strengths and weaknesses of a project

The correct answer is: Industry studies of similar projects by risk specialists

Industry studies of similar projects by risk specialists can be an enterprise environmental factor influencing performing qualitative risk analysis. These studies provide valuable insights into the risks that similar projects have faced in the industry, allowing project teams to learn from past experiences and apply relevant risk management strategies. By leveraging industry expertise and knowledge, project teams can better understand potential risks and their potential impact on project objectives, thus enhancing the qualitative risk analysis process. The other options listed do not directly relate to enterprise environmental factors that influence qualitative risk analysis. While the list of identified risks, risk urgency assessment, and strengths and weaknesses of a project are important considerations in risk management, they do not specifically pertain to external industry studies conducted by risk specialists, which can greatly enhance the risk analysis process.