CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the CAPM Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What could result from a lack of tracking updates in project documents?

  1. Scope creep

  2. Weakened end results for a project

  3. Budget overrun

  4. Unsatisfied stakeholders

The correct answer is: Weakened end results for a project

This is because without regular tracking updates, a project may fall behind schedule or fail to meet its objectives, resulting in weaker end results. Option A, scope creep, refers to a project's scope expanding beyond its original boundaries, often leading to increased costs and delays. Option C, budget overrun, is a common consequence of scope creep, where a project exceeds its budget due to additional tasks and changes. Option D, unsatisfied stakeholders, may occur if project delivery is delayed or objectives are not met, leading to dissatisfaction among project sponsors, clients, or users. However, option B is the most direct result of a lack of tracking updates in project documents, as it directly impacts the quality and success of the project's final outcomes.