What do activity attributes describe?

  1. The quality requirements needed for activity completion

  2. The detailed characteristics of each activity including description and person responsible

  3. The costs associated with each project activity

  4. The risks linked to each project activity

The correct answer is: The detailed characteristics of each activity including description and person responsible

Activity attributes describe the detailed characteristics of each activity including description and person responsible. Option A is incorrect because quality requirements are described in Quality metrics and checklists, not activity attributes. Option C is incorrect because costs associated with each project activity are described in the Cost Management Plan, not activity attributes. Option D is incorrect because risks linked to each project activity are described in the Risk Management Plan, not activity attributes.