CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the CAPM Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What do activity duration estimates not include?

  1. Reserve analysis adjustments

  2. Lags

  3. A range of time periods

  4. Quantitative assessments of time periods

The correct answer is: Lags

Activity duration estimates include the time required to complete an activity without considering any delays or waiting time, which are represented by lags. Lags refer to the waiting time between activities and are not included in the primary activity duration estimates. Therefore, the correct answer is B. Reserve analysis adjustments (Choice A), a range of time periods (Choice C), and quantitative assessments of time periods (Choice D) are all factors that can be considered in developing activity duration estimates.