What do resource calendars in the acquire project team process show?

  1. The roles of team members

  2. The availability of team members

  3. Project budget estimates

  4. Project timelines

The correct answer is: The availability of team members

Resource calendars in the acquire project team process show the availability of team members. This information is critical in planning project tasks and timelines, as it allows project managers to understand which team members are able to work on specific tasks and when. Option A is incorrect because while resource calendars may include team member roles, that is not their primary purpose. Option C is incorrect because project budget estimates are typically found in the project budget, not in resource calendars. Option D is incorrect because project timelines are typically found in the project schedule, not in resource calendars.