CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the CAPM Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What does a negative Cost Variance (CV) indicate?

  1. Costs are exactly as budgeted

  2. Costs are overrun

  3. Costs are below budget

  4. The project is behind schedule

The correct answer is: Costs are overrun

A negative Cost Variance (CV) indicates that costs are overrun. In other words, the actual costs incurred are higher than what was budgeted for the project. This can be problematic as it means that the project is spending more money than planned, which can impact the overall budget and profitability of the project. Option A is incorrect because a negative CV does not mean costs are exactly as budgeted. Option C is incorrect as a negative CV does not indicate costs are below budget. Option D is incorrect as a negative CV is related to costs rather than the project schedule.