CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the CAPM Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What does 'predecessor' mean in project scheduling?

  1. The initial phase of the project

  2. A task that provides resources for the project

  3. The final activity of the project

  4. The activity that must happen first when defining dependencies between activities in a network

The correct answer is: The activity that must happen first when defining dependencies between activities in a network

In project scheduling, a 'predecessor' refers to the activity that must happen first when defining dependencies between activities in a network. This means that the predecessor task must be completed before the successor task can begin. It helps in determining the logical sequence of activities in a project to ensure its successful completion. This is why option D is the correct answer. Options A, B, and C do not accurately define what a 'predecessor' means in project scheduling. The initial phase of the project (Option A) does not specifically relate to the relationship between activities, a task that provides resources for the project (Option B) is not what 'predecessor' signifies, and the final activity of the project (Option C) is referred to as a 'successor' rather than a 'predecessor' in project scheduling terminology.