CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $4.99 payment

Study for the CAPM Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Practice this question and more.


What does Project Scope Management aim to avoid?

  1. Budget Overruns

  2. Scope Creep

  3. Schedule Delays

  4. Quality Issues

The correct answer is: Scope Creep

Project Scope Management aims to avoid scope creep, which refers to the continuous growth or addition of new requirements, features or requests throughout the course of a project. This can result in delays, cost overruns, and potential quality issues as the project team may not have enough time or resources to properly address the additional requirements. Budget overruns, schedule delays, and quality issues are indirect results of scope creep. Therefore, options A, C, and D are incorrect as they do not directly correspond to the main focus of Project Scope Management.