What does resource leveling aim to achieve?

  1. Reduce project costs

  2. Balance demand with supply based on resource constraints

  3. Increase stakeholder satisfaction

  4. Improve team communication

The correct answer is: Balance demand with supply based on resource constraints

Resource leveling aims to balance the demand for resources with the available supply, while taking into consideration any resource constraints that may exist. Option A is incorrect because while resource leveling may result in reduced project costs, it is not the main objective of this technique. Option C is incorrect because while stakeholder satisfaction may indirectly benefit from resource leveling, it is not the primary goal. Option D is incorrect because while improved team communication may be a result of resource leveling, it is not the primary purpose of this technique.