What does the contract change control system define?

  1. Project scope

  2. Modification process of the procurement

  3. Seller's deliverable dates

  4. Time management system

The correct answer is: Modification process of the procurement

The contract change control system defines the process of handling changes to the procurement, such as modifications to the scope of work, pricing, or terms and conditions. This system is used to ensure that all changes are properly documented, evaluated, and approved or rejected in a timely manner. Option A is incorrect because it specifically refers to project scope, whereas the contract change control system encompasses all aspects of the procurement. Option C is incorrect because it only mentions the seller's deliverable dates, which is just one component of the procurement and not the focus of the contract change control system. Option D is also incorrect as it only pertains to time management, which is not the main purpose of the contract change control system.