CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the CAPM Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What does the critical path method aim to identify?

  1. The shortest path to complete the project

  2. The most cost-effective path to complete the project

  3. The longest sequence of dependent tasks

  4. The most resource-intensive tasks

The correct answer is: The longest sequence of dependent tasks

The critical path method is a project management tool that aims to identify the longest sequence of dependent tasks in a project. This is important because if any of these tasks are delayed, it could delay the entire project. Unlike options A and B, the critical path method does not focus on the shortest or most cost-effective path, but rather the sequence of tasks with the longest duration. Option D is also incorrect as the critical path method does not solely focus on identifying the most resource-intensive tasks, but rather the overall sequence of dependent tasks. Therefore, option C is the correct answer as it accurately describes the goal of the critical path method.