What does the procurement statement of work define?

  1. The portion to be included within contract

  2. The total budget of the project

  3. The project's deliverables

  4. The project's scope statement

The correct answer is: The portion to be included within contract

The procurement statement of work defines the portion of the project that will be included in the contract, which outlines the specific goods or services being procured. While the total budget (B) and project's deliverables (C) may be mentioned in the procurement statement of work, they are not the main focus. The project's scope statement (D) may also be referenced, but it is not the same as the procurement statement of work, which specifically outlines the contracted portion of the project. Therefore, option A is the most accurate and relevant answer.