What does the requirements management plan describe?

  1. How the project's expenses will be managed

  2. How requirements will be analyzed, documented, and managed

  3. The project's communication plan

  4. The project's risk management strategies

The correct answer is: How requirements will be analyzed, documented, and managed

The requirements management plan describes how requirements will be analyzed, documented, and managed throughout the project. This plan outlines the process for gathering, documenting, prioritizing, and maintaining project requirements. It ensures that all project stakeholders have a clear understanding of what needs to be delivered and helps prevent scope creep by managing changes to requirements effectively. Option A is incorrect because it refers to cost management, which is not the primary focus of the requirements management plan. Option C is incorrect as the communication plan is a separate document that outlines how project communication will be managed. Option D is incorrect as risk management strategies are detailed in the risk management plan, not the requirements management plan.