CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the CAPM Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What does the Schedule Performance Index (SPI) specifically measure?

  1. Cost efficiency of the project

  2. Schedule efficiency of the project

  3. Total cost at the completion of the project

  4. Total budget of the project

The correct answer is: Schedule efficiency of the project

The Schedule Performance Index (SPI) specifically measures the schedule efficiency of the project. It is a crucial metric in project management that indicates the project's progress in terms of scheduled tasks completed compared to the planned schedule. A value of SPI equal to 1 indicates that the project is right on track, values greater than 1 show ahead of schedule performance, and values less than 1 indicate delays in the project schedule. Option A, the cost efficiency of the project, is measured by the Cost Performance Index (CPI), not SPI. Option C, the total cost at the completion of the project, is measured by the Estimate at Completion (EAC) calculations. Option D, the total budget of the project, is not specifically measured by the SPI; it is more related to the Budget at Completion (BAC) in project management terms.