What does the scope baseline include?

  1. Project charter

  2. The project scope statement, WBS, and WBS dictionary

  3. Requirements documentation

  4. Cost baseline

The correct answer is: The project scope statement, WBS, and WBS dictionary

The scope baseline includes all the detailed information related to the project scope and requirements. This includes the project scope statement, work breakdown structure (WBS), and WBS dictionary. Option A, the project charter, is incorrect because the scope baseline is a part of the project management plan, which is created after the project charter is approved. Option C, requirements documentation, is also incorrect because while requirements are a part of the scope baseline, they are not the only component. Option D, the cost baseline, is incorrect because it is a part of the cost management plan, not the scope baseline.