What does the WBS dictionary house?

  1. The project's budget allocations

  2. The high-level project requirements

  3. The details associated with the work packages and control accounts

  4. The project's schedule milestones

The correct answer is: The details associated with the work packages and control accounts

The correct answer is C. The WBS dictionary houses the details associated with the work packages and control accounts. It provides a detailed description of the work to be done in each work package, including the scope of work, deliverables, resources required, budget information, quality criteria, and other relevant details. This document helps ensure that everyone involved in the project understands the work to be performed and how it will be measured and controlled. Options A, B, and D are incorrect because the project's budget allocations, high-level project requirements, and project schedule milestones are typically not housed in the WBS dictionary. These aspects are usually documented in the project's budget, project requirements documentation, and project schedule, respectively.