CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the CAPM Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What form of updates are considered part of org process assets updates from managing stakeholder engagement?

  1. Project reports, project presentations

  2. Stakeholder engagement metrics

  3. Resource allocation plans

  4. Budget forecasts

The correct answer is: Project reports, project presentations

Project reports and project presentations are considered part of org process assets updates from managing stakeholder engagement because they are the primary communication tools used to keep stakeholders informed and engaged in the project. These updates provide stakeholders with key information on project progress, issues, risks, and decisions which are essential for maintaining stakeholder engagement and support throughout the project lifecycle. Stakeholder engagement metrics, resource allocation plans, and budget forecasts are important aspects related to managing stakeholders, but they are not direct forms of updates that are typically included in org process assets updates from managing stakeholder engagement.