What is a change log?

  1. A document listing all stakeholders

  2. A structured review of the procurement process

  3. A formal authorization for project changes

  4. A comprehensive list of changes made during a project

The correct answer is: A comprehensive list of changes made during a project

A change log is a comprehensive list of changes made during a project. It serves as a documented record of all changes that have been identified, requested, or implemented throughout the project's lifecycle. By maintaining a change log, project managers can track the evolution of the project, understand the impact of various changes, and ensure that stakeholders are informed about modifications to the project scope, schedule, or cost. This record helps in maintaining transparency, accountability, and effective communication within the project team. Options A, B, and C are incorrect because they do not accurately describe what a change log is. A change log is specifically focused on documenting changes made during a project, rather than listing stakeholders, reviewing procurement processes, or providing formal authorization for changes.