What is an output of the develop schedule process?

  1. Risk management plan

  2. Schedule baseline

  3. Quality metrics

  4. Stakeholder engagement plan

The correct answer is: Schedule baseline

The correct answer is B: Schedule baseline. During the Develop Schedule process, one of the key outputs is the Schedule Baseline. The Schedule Baseline is a configuration management tool that represents the approved version of the project schedule. It includes the project schedule, plus or minus approved changes. The Schedule Baseline is used as a basis to measure and monitor project progress and performance throughout the project lifecycle. The other options are outputs of different processes: - The Risk Management Plan is an output of the Plan Risk Management process. - Quality metrics are typically an output of the Plan Quality Management process. - The Stakeholder Engagement Plan is usually an output of the Identify Stakeholders process.