CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the CAPM Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What is an output of the Plan Quality Management process?

  1. Quality control measurements

  2. Resource calendars

  3. Quality management plan

  4. Stakeholder engagement plan

The correct answer is: Quality management plan

The correct answer is C. Quality management plan. During the Plan Quality Management process, the main output is the Quality Management Plan. This document outlines how quality policies, objectives, and responsibilities will be implemented to achieve the required quality for the project. It describes the quality standards that will be used, quality control and quality assurance activities, and the tools and techniques that will be utilized throughout the project to ensure the quality requirements are met. While the other options may be related to project management processes, they are not specific outputs of the Plan Quality Management process. Options A, B, and D are not direct outputs of the Plan Quality Management process but are related to other aspects of project management.