What is measured by technical performance measurement during project execution?

  1. Financial expenses

  2. Team productivity

  3. Technical accomplishments versus scheduled technical achievement

  4. Progress of risk management

The correct answer is: Technical accomplishments versus scheduled technical achievement

Technical performance measurement during project execution focuses on evaluating technical accomplishments against scheduled technical achievements. This helps in assessing whether the project is progressing as planned in terms of technical goals and milestones. Options A, B, and D do not directly relate to the measurement of technical performance during project execution and are therefore incorrect in this context.