CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the CAPM Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What is the main goal of performing quantitative risk analysis?

  1. To update the project management plan

  2. To identify new risks

  3. Numerically analyzing the effect of identified risks on overall project objectives

  4. To assign resources to risk responses

The correct answer is: Numerically analyzing the effect of identified risks on overall project objectives

Quantitative risk analysis is used to assess and measure the impact of identified risks on the overall project objectives. This includes assigning numerical values to risks, analyzing their potential effects, and prioritizing the risks based on their potential impact. This process is not used to update the project management plan (option A), as that is typically done during risk planning. Identifying new risks (option B) is part of the risk identification process, not the quantitative risk analysis process. Assigning resources to risk responses (option D) is done during risk planning and is not the main goal of quantitative risk analysis.