What is the primary output of identifying risks?

  1. Risk register

  2. Risk matrix

  3. Risk report

  4. Risk analysis document

The correct answer is: Risk register

The primary output of identifying risks is the risk register. The risk register is a document that includes all identified risks, their potential impact, probability of occurrence, triggers, owner, responses, and current status. It serves as a central repository for all risk-related information and is a key tool for managing risks throughout the project. While the other options (risk matrix, risk report, and risk analysis document) are also important in risk management, the risk register is specifically designed to capture and document the identified risks for effective monitoring and control.