What is the schedule baseline?

  1. A tentative project schedule

  2. A detailed risk analysis

  3. The approved version of a schedule model for comparison to actual results

  4. A preliminary project budget

The correct answer is: The approved version of a schedule model for comparison to actual results

The schedule baseline is the approved version of a schedule model that serves as the basis for measuring and monitoring project progress. Option A, a tentative project schedule, may not have been approved and is subject to change. Option B, a detailed risk analysis, is a different aspect of project planning and does not pertain to the schedule. Option D, a preliminary project budget, is also a different aspect of project planning and does not specifically pertain to the schedule. Therefore, the best answer is C.