Which are tools and techniques used in the 'Direct and Manage Project Work' process?

  1. Benchmarking, SWOT analysis, and checklists

  2. Expert judgment, PMIS, and meetings

  3. Earned value management, variance analysis, and trend analysis

  4. Inspections, audits, and design thinking

The correct answer is: Expert judgment, PMIS, and meetings

The 'Direct and Manage Project Work' process involves executing the project management plan to complete the project deliverables. In this process, it is essential to utilize tools and techniques that facilitate effective project execution. Option B, consisting of expert judgment, Project Management Information System (PMIS), and meetings, is the correct answer. Expert judgment provides valuable insights from individuals with specialized knowledge or experience. PMIS helps in tracking and managing project performance. Meetings ensure communication among team members, stakeholders, and decision-makers, enhancing collaboration and problem-solving. Options A, C, and D are incorrect as they contain tools and techniques that are more commonly associated with other processes within project management, such as planning, monitoring and controlling, or quality management.