Which is NOT a tool or technique of control stakeholder engagement?

  1. Information management systems

  2. Communication methods

  3. Meetings

  4. Expert judgment

The correct answer is: Communication methods

Control stakeholder engagement is a process that ensures stakeholders are effectively involved and informed in a project. The main purpose of this process is to manage the stakeholder relationships and keep them engaged throughout the project. In order to achieve this, various tools and techniques such as information management systems, meetings, and expert judgement are used. These tools and techniques help in exchanging information, making decisions, and resolving conflicts with stakeholders. Option B, communication methods, is incorrect because it is an essential part of control stakeholder engagement and is used to enable effective communication with stakeholders. Therefore, it is not the correct answer. Options A, C, and D are all valid tools and techniques of control stakeholder engagement. Information management systems are used to store and organize stakeholder information, meetings are used to discuss project updates and collaborate with stakeholders, and expert judgement is used to make informed decisions about stakeholder engagement. Therefore, they are all incorrect answers.