CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the CAPM Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Which is NOT listed as a tool or technique of Plan Quality Management?

  1. Statistical sampling

  2. Employee surveys

  3. Cost of quality

  4. Design of experiments

The correct answer is: Employee surveys

Employee surveys are not listed as a tool or technique of Plan Quality Management because they are typically used in Resource Management or Communications Management. Plan Quality Management focuses on establishing quality requirements and standards for the project and ensuring that the project will meet those requirements. Statistical sampling, cost of quality, and design of experiments are all tools and techniques that can be used to help plan and manage the quality of a project.