CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the CAPM Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Which of the following is a tool or technique for controlling risks?

  1. Risk reassessment

  2. Work performance info

  3. Change requests

  4. Project management plan updates

The correct answer is: Risk reassessment

Answer A, Risk reassessment, is the correct answer in this case because it is a method used to monitor and review risks throughout a project. This involves regularly reviewing the risk management plan and making adjustments as necessary to ensure that risks are being properly identified, analyzed, and responded to. Option B, Work performance info, is incorrect because it refers to information on how the project is progressing, not a specific tool or technique for controlling risks. Option C, Change requests, is incorrect because they are used to request modifications to project scope, schedule, or other aspects, not for controlling risks specifically. Option D, Project management plan updates, is a broad term that could encompass various changes to the overall plan, but does not specifically refer to controlling risks.