Which of the following is not an output of the control communications process?

  1. Project documents updates

  2. Project charter updates

  3. Organizational process assets updates

  4. Change requests

The correct answer is: Project charter updates

The project charter is considered as an input to the control communications process, where the performance of the project is monitored and any necessary changes are implemented. The other options, such as project documents updates, organizational process assets updates, and change requests, can all be outputs of the control communications process as they are all related to managing and documenting project information.