Which of the following is not an organisational process asset that can influence manage project team?

  1. Bonus structures

  2. Corporate apparel

  3. Project schedule

  4. Newsletters

The correct answer is: Project schedule

Organisational process assets are documents, templates, policies, and procedures that are used by an organization to influence and guide project management processes. Bonus structures, corporate apparel, and newsletters are all examples of organisational process assets that can influence the manage project team process. However, the project schedule is not an organisational process asset as it is a tool used to plan, monitor, and control project activities. While it is an important component of project management, it is not considered an asset in the same way as documents and policies. Therefore, C is the correct answer as it is the only option that is not an organisational process asset.