Which of the following is a typical output of the determine budget process?

  1. Resource calendars

  2. Project funding requirements

  3. Stakeholder engagement plan

  4. Communications breakdown structure

The correct answer is: Project funding requirements

The correct answer is B. Project funding requirements. During the Determine Budget process, one of the key outputs is to establish the cost baseline for the project, including the funding needed to execute the project successfully. This output outlines the financial resources required for the project activities, enabling the project manager to allocate funds appropriately and manage the project within the approved budget. Option A, Resource calendars, is typically an output of the Develop Schedule process, not the Determine Budget process. Option C, Stakeholder engagement plan, is an output of the Plan Stakeholder Engagement process. Option D, Communications breakdown structure, is not a standard output of any Project Management process.