Which of the following is not one of the 3 baseline plans?

  1. Scope baseline plan

  2. Schedule baseline plan

  3. Cost baseline plan

  4. Quality baseline plan

The correct answer is: Quality baseline plan

The correct answer is D, Quality baseline plan. In project management, the three baseline plans are the Scope baseline plan, Schedule baseline plan, and Cost baseline plan. These three baselines are essential for monitoring and controlling the project throughout its lifecycle. The Quality baseline plan is not one of the main baseline plans in project management, although quality management is crucial for project success.