Which of the following would not be considered a tool and technique of control communications?

  1. Expert judgment

  2. Performance reporting

  3. Meetings

  4. Information management systems

The correct answer is: Performance reporting

Performance reporting is not considered a tool and technique of control communications because it is a primary output of the control communications process. It is a way to formally document and communicate the progress and status of project communications. Expert judgment, meetings, and information management systems are all tools and techniques used in control communications to ensure effective and efficient communication throughout the project.