CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the CAPM Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Which tool or technique is used in the estimate activity resources process?

  1. SWOT Analysis

  2. Expert judgment

  3. Stakeholder engagement

  4. Cost-benefit analysis

The correct answer is: Expert judgment

Expert judgment is the most appropriate tool or technique for the estimate activity resources process because it involves utilizing the knowledge and experience of subject matter experts to estimate the resources needed for a particular activity. Options A, C, and D are not applicable in this process because SWOT Analysis is used for strategic planning, stakeholder engagement for managing stakeholder interactions, and cost-benefit analysis for analyzing the costs and benefits of a proposed project. Therefore, none of these options are as relevant and effective as expert judgment in the estimate activity resources process.