CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the CAPM Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Whose responsibility is it to ensure that work performance information is captured?

  1. Project sponsor

  2. Project manager

  3. Team leader

  4. Customer

The correct answer is: Project manager

The project manager is responsible for ensuring that work performance information is captured. This responsibility falls under the project manager's role to monitor and control the project activities. By capturing work performance information, the project manager can analyze the progress, identify any deviations from the project plan, and take corrective actions as necessary to keep the project on track. The project sponsor plays a crucial role in supporting the project, securing resources, and providing high-level direction but is not directly responsible for capturing work performance information. The team leader's responsibility is to lead and manage a specific team within the project, while the customer is more involved in defining project requirements and providing feedback rather than capturing work performance information.